Electric Vehicle Charging

Electric Vehicle Charging

Electric Vehicle Infrastructure Site Preparation

LOCATION: San Bernardino, California

CUSTOMERSan Bernardino County Transportation Authority

PROJECT SCOPEWork consists of installing radar feedback signs, solar panels and hardware on existing street light poles or on new 1-A poles.

CHARACTERISTICS: Installed 12 solar powered feedback signs at various locations.

START AND FINISH DATE: May 2021 to March 2022

Electric Vehicle Infrastructure Site Preparation

Electric Charging Vehicle Station Bonita Ave

LOCATION: San Dimas, California

CUSTOMERCity of San Dimas

PROJECT SCOPETrenching, placing conduits, installing four EV charging stations at three locations, electrical work, backfilling and flat work.

CHARACTERISTICS:  EV charging stations were operational just three weeks after the contract award, meeting the agency's stringent requirements.

START AND FINISH DATE: August 2019 to October 2019

Electric Charging Vehicle Station Bonita Ave

Electric Bus Charging Station for Norwalk Transit System

LOCATION: Norwalk, California

CUSTOMER: City of Norwalk

PROJECT SCOPEInstallation of (4) EV Charging Stations including conduit, wiring and concrete restoration.

CHARACTERISTICS: The project required Elecnor Belco's certification for EV installation.

START AND FINISH DATE: November 2021 to January 2022

Electric Bus Charging Station for Norwalk Transit System